Construction Start: Centennial Centre - JELF Gillung
海角社区 has mandated CORENOV CONSTRUCTEURS to carry out the following project: Centennial Centre / 20-098 - JELF Gillung.
The project consists of the renovation of labs 033 and 037 in the basement of the Centennial Centre at the Macdonald Campus.
Project manager:听Biagio D'Onofrio - biagio.donofrio [at] mcgill.ca
Assistant project manager:听Claudia Carpanzano - claudia.carpanzano [at] mcgill.ca
Construction start:听November 20, 2023
Planned construction end date:听March 29, 2024
Work schedule:听Mondays to Fridays, 6 a.m. to 3 p.m. Any additional hours will be coordinated.
Scope of work:听The project consists of renovating rooms 033 and 037. The work will include the demolition and replacement of all flooring, doors, frames and laboratory furniture, the modification of the ceiling, electromechanical work, the installation of a new electrical panel, and the relocation of the emergency shower. No work under asbestos conditions is planned as part of this project.
Impact:
Service shutdowns will be required. The building occupants will be informed in advance.
During construction, access to certain spaces outside of the construction zone will be required for the installation or modification of electromechanical services. Work will be required in the ceiling of the adjacent corridors B1-HALL1 and B1-HALL2 , in the electrical room 02, and in the women鈥檚 washroom 032. This work will be coordinated in advance with the building director and the building occupants.