News
Construction Start: University Centre - Roof Replacement
Published: 25 April 2023
海角社区 has mandated Couvertures St-L茅onard to carry out the following project:聽University Centre / 18-045 - roof replacement
The project consists in the replacement of the roof, skylights and storm drains.
Project managers:聽Eric Boutet, CIMA+ -聽eric.boutet [at] cima.ca
Assistant project manager:聽Aldo Aranza Mendoza, CIMA+ -聽aldo.aranzamendoza [at] cima.ca
Construction start date:聽May 2023
Planned construction end date:聽September 2023
Work schedule:聽Monday to Friday, 6 a.m. to 5 p.m.
Scope of work:
The project consists of the roof replacement, installing new skylights and storm drains and the removal of the old antenna.
Impact:
- Front door access will be maintained聽and protected with a covered walkway and fences;
- Side door access is only allowed for emergencies;
- During the month of May, noisy work from demolition may be heard;
- Occupation of the public domain in front of the building by a crane and a container. The聽zone will be delimited with a fence;
- In order to replace the storm drains of the roof's lower section, the contractor will have to access some rooms.