Nouvelles
Construction Start: MNI - Cyclotron
±Ê³Ü²ú±ô¾±Ã©: 17 May 2023
º£½ÇÉçÇø has mandated ARDEC to carry out the following project: Montreal Neurological Institute / 18-121 - Cyclotron.
The project consists of replacing the cyclotron's conduit.
Project manager:Â Eric Boutet, CIMA+ -Â eric.boutet [at] cima.ca
Assistant project manager:Â Aldo Aranza Mendoza, CIMA+ -Â aldo.aranzamendoza [at] cima.ca
Construction start:Â May 19, 2023
Planned construction end date:Â May 29, 2023
Work schedule:Â Monday to Friday, 7 a.m. to 3 p.m.
Scope of work:
The work is on the exterior of the building and includes the installation of a conduit on the roof of the MNI building.
Impact:
There will be no impact on the building users, however, a crane will be used on May 19th.Â